Operation and Maintenance (O&M) Manual for Energy Transmission Cable Plant.
The Contractor shall be
responsible for compiling operation and maintenance (O&M) manuals for each
section of the Works.
Drafts of the manuals are to
be submitted to the Engineer at least six weeks prior to the commencement of
pre-energization commissioning checks on Site. Following the examination, The engineer will forward copies of his comments to the Contractor for action prior
to issuing Final O&M manuals. Final O&M manuals are to be available on-site prior to the issue of the Taking over Certificate.
Handling, installation, storage, and transit instructions, in accordance with Clause 7 of BS 4884 part
1, which shall form part of the manuals, are to be available on-site prior to
the arrival of the Plant.
In addition to the compiled
manuals, the contractor shall submit copies of brochures and other explanatory
literature with drawings of the plant, which will assist the Engineer in
approval of the drawings.
Contents of Operation and Maintenance Manuals
Operation and Maintenance
manuals shall be prepared for the equipment supplied for the substation. The
content and presentation of the manuals shall conform in full with BS 4884 parts 1 and 2.
The O&M manuals are also
to contain a complete drawing list appropriate to the individual section of the
works. The drawing list shall include the Engineer’s drawing numbers.
Maintenance instructions for
all plants shall cover preventive and corrective maintenance procedures. For
electronic or solid-state control, protection equipment, etc. details shall be
provided to enable individual circuit cards to be checked for correct operation
and faults to be traced, and repaired.
The Contractor shall provide
preformed of the required maintenance record sheets for all plants, which shall
include a cross-reference to the appropriate section of the O&M manuals which
detail how to perform the tasks required. Any other record sheets suitable for
the monitoring of the plant shall also be designed and provided.
Binders, Presentation of Operation and
Maintenance Manuals
The information will be
provided on A4 pages, with diagrams on throw-clear pages where required to
enable the text and diagrams to be referred to simultaneously.
The front cover and spine of
the manuals shall give the following information:
- Project Title;
- Employer’s name;
- Contract number;
- Identification of the Section of the Works;
- The volume number and the total number of volumes applicable;
- Contractor’s company logo and name;
The above shall also be
provided on a flysheet inside the front cover of each volume. Draft O&M
manuals may be presented in unprinted covers.
Four copies of draft O&M
manuals are to be provided to the Engineer; following approval 8 copies are to
be provided to the Engineer or Engineer’s site Representative for each section
of the works.