The Contractor shall be
responsible for the submission to the engineer of all plant supplied under the
contract for inspection and testing during site erection, to ensure correct
erection and compliance with the specification.
During the course of
erection, the Contractor shall provide access as required by the Engineer for
inspecting the progress of the works and checking its accuracy to any extent
that may be required.
The Contractor shall provide,
at his own cost, all labour, materials, stores, and apparatus as may be
requisite and as may be reasonable demanded to carry out all tests during
erection, whether or not the tests are specifically referred to in this
specification.
Tests on completion of
erection shall be carried out by the contractor in accordance with the General
conditions of Contract. The Contractor shall provide all necessary test
equipment to carry out the site tests, but where required in the Schedule of
Prices, shall include the cost of the equipment so that the Employer may have
the option to buy the equipment on completion of the Contract.
Sponsored:
Sponsored:
The Contractor shall submit a
written program of tests and checks according to this Clause for the approval
of the Engineer.
A brief description of all
tests and testing procedures shall be provided before tests commence and the
method of testing, unless otherwise specified, shall be agreed with the
Engineer.
The Contractor shall provide
experienced test personnel and testing shall be carried out during normal
working hours as far as is practicable. Tests which involve existing apparatus
and outages may be carried out outside normal working hours. The Contractor
shall give sufficient notice to allow for the necessary outage arrangements to
be made in conformity with the testing program.
The Contractor shall advise
the Engineer in writing, at the time of commencement of site erection, of the
site supplies which will be required for the operation of the test equipment,
to enable the Engineer to arrange accordingly or to agree alternative
arrangements should this be necessary.
The Contractor shall rector
shall record the results of the tests clearly, on an approved form and with
clear reference to the equipment and items to which they refer, so that the
record can be used as the basis for maintenance test during the working life of
the equipment. The required number of site test result records shall be
provided by the contractor to the Engineer as soon as possible after completion
of the tests.
No tests as agreed under the
program of tests shall be waived except upon the instruction or agreement of
the Engineer in writing.
The Contractor’s test
equipment shall be of satisfactory quality and condition and, where necessary,
shall be appropriately calibrated by an approved authority at the Contractor’s
expense. Details of the test equipment and instruments used shall be noted in
the test sheets in cases where the instrument or equipment characteristics can
have a bearing on the test results.
The testing requirementsdetailed under this Specification may be subject to some variation upon the
instruction or agreement of the engineer where necessitated by change
conditions at Site of by differing design, manufacture, or construction
techniques.
The tenderer is required to
submit proposals for site dielectric tests and to include in his price the
costs of such tests and of such equipment as deemed necessary.
Image result for inspection and testing procedure, Electrical Inspection and Testing is a procedure completed by qualified electricians. Electrical installations that comply with BS 7671 are likely to satisfy Statutory Regulations such as the Electricity at Work Regulations 1989.
Sponsored:
Image result for inspection and testing procedure, Electrical Inspection and Testing is a procedure completed by qualified electricians. Electrical installations that comply with BS 7671 are likely to satisfy Statutory Regulations such as the Electricity at Work Regulations 1989.
Sponsored:
No comments:
Post a Comment
WAZIPOINT:
Thank you very much to visit and valuable comments on this blog post. Keep in touch for next and new article. Share your friends and well-wisher, share your idea to worldwide.