High Voltage Test Guide for Power Cables
A complete high-voltage test guide for power cables is essential for both cable users and contractors to get a clear idea about cable pre-commissioning and commissioning.
Underground power cables should be tested before on-site commissioning or re-commissioning is known as SAT or Site-Acceptance-Test. Although cables are tested by the manufacturer in their factory are known as FAT or Factory-Acceptance-Test before delivery.
FAT ensured the quality and specifications of the cables that followed international standards (like IEC, IEEE, BS) and customer’s requirements; on the other hand, SAT is limited in that it gives no information about the quality of the circuit.
The summary of this test results is simply just PASS or FAIL information, but this test gives the user a very degree of confidence that when they switch on to energize the line will operate satisfactorily.
Underground power cables should be tested before on-site commissioning or re-commissioning is known as SAT or Site-Acceptance-Test. Although cables are tested by the manufacturer in their factory are known as FAT or Factory-Acceptance-Test before delivery.
FAT ensured the quality and specifications of the cables that followed international standards (like IEC, IEEE, BS) and customer’s requirements; on the other hand, SAT is limited in that it gives no information about the quality of the circuit.
The summary of this test results is simply just PASS or FAIL information, but this test gives the user a very degree of confidence that when they switch on to energize the line will operate satisfactorily.
Cable testing at the site
gives the satisfaction that during laying and carrying there happened no
damage. So, cable testing including joints, terminations, and all other accessories on site before switching on the power is mandatory for line construction
companies and operators.
The cable should be tested as per national or internationally specified specifications where the applied voltage level and duration are mentioned.
The cable should be tested as per national or internationally specified specifications where the applied voltage level and duration are mentioned.
e.g- for 33kV medium voltage underground cable Hipot test voltage 3
times of rated voltage for 15 minutes duration. This means the rated voltage per phase is 33kV/1.732=19kV, so applied voltage = (19x3)kV = 57kV DC for 15 minutes.
Similarly for 132kV cable, the test voltage is (132/1.732)x3=228kV for 15
minutes. Of course, the time duration varies from cable manufacture to manufacture
specification.
If at the end of the test
time the circuit has withstood the applied voltage, then it gives the satisfactory
result PASS; otherwise, FAIL.
Getting
Ready to Start High Voltage Test:
Sponsored Link:
Consider the following points before starting the Hi-Pot or High Voltage test performed.
All equipment must be disconnected from the cable circuit, i.e., taps, motors, circuit breakers, surge arrestors, etc. This will prevent damage or interruption to such equipment from excessive leakage current.
Establish adequate clearance between the circuit test ends and any grounded object, and to other equipment not under test, also keep all personnel at a safe distance.
Ensure grounding of all circuit conductors except under test with all cable shields including nearby types of equipment.
Ensure specified maximum test voltage, recommendations time duration for termination, and others accessories.
Procedure to apply voltage:
Voltage may apply the Continuous method or step method as per specification.
Continuous Method:
Apply
test voltage at an approximate rise rate of 1 kV per second or 75% of the rated
current output of the equipment, whichever is less. Some equipment will take
longer to reach the maximum test voltage because of the amount of charging current.
Step Method: Apply test
voltage slowly in 5 To 7 Increments of equal value to the maximum specified. Allow
sufficient time at each stop for the leakage current to stabilize.
Caution: Don’t forget, DC charges on
cable can build up to potentially dangerous levels if grounds are removed too
quickly. Maintain solid grounds after the test on the cable for at least 4
times the duration of the test.
Sponsored:
very informative blog..keep update with your blogs..
ReplyDeletecable pulling tools
we must select carefully and buy from the best power cable manufacturers
ReplyDelete