WAZIPOINT Engineering Science & Technology: XLPE CABLE COMMISSIONING TEST PROCEDURE FOLLOWING IEC STANDARD

Wednesday, March 13, 2019

XLPE CABLE COMMISSIONING TEST PROCEDURE FOLLOWING IEC STANDARD

XLPE Insulated Power Cable Commissioning Test Procedure as per IEC Standard

After completion of the installation work of the underground power transmission cable line, the commissioning test must be carried out just before energizing the plant. This article demonstrates the practical commissioning test procedure for extra high voltage (EHV) and high voltage (HV) underground power cables.
The following commissioning test should be carried out step by step:
·        Phasing Verification;
·        10kV DC Sheath Integrity Test;
·        Cable Insulation Resistance Measurement (IR);
·        Capacitance Measurement;
·        High Voltage AC Test.

Phasing Verification Test

·        Test Purpose: To ensure the continuity and phasing of the cable conductor from terminal to terminal
·        Test Equipment: Megger Tester (BM21 or Equivalent)
·        Requirement: There are not any discontinuities of the cable conductor.
Cable Phasing Check
Procedure
Conductor continuity and phasing test will be performed after completion of all splices and terminations installation.

Phasing tests will be carried out by using the main conductor as shown in Figure, where the phase undergoing the test is grounded while the other two phases of the cable are opened.

The cable conductor shall be tested using a minimum of DC 1kV per phase as below figure


10kV DC Sheath Test

·        Test Purpose: DC 10kV test shall be performed to confirm the soundness and integrity of the cable sheath.
·        Standard: According to clause 14.1 of IEC 62067
·        Test Equipment: DC Voltage Tester (Baur PGK 80 or Hi-Leakester or Equivalent)
·        Requirement: No breakdown shall have occurred.
10 kV DC Sheath Test
Procedure
During the testing period, all necessary safety measures have to be taken into consideration. Special note must be taken of exposed metalwork that will be at test potential during the procedure e.g. cable termination bell housings.

The IRs of each cable sheath (between Al sheath and ground) will be measured at 5kV for 1 minute. The shields of cables not being tested will be grounded during IR measurement.

The tests will be applied at the shield grounding link box at one end of the circuit. At the link box at the far end of the circuit from the testing location, the links and/or SVLs will be removed. The link box will be closed and locked and a notice warning of testing in progress posted. If exposed metalwork that will be hazardous during testing exists appropriate warning signs and a watchman must be posted to prevent accidental contact by any person.

At the testing end link-box the links and/or SVLs will be removed. The two-phase cables not under test will be grounded by jumper leads. The 10kV DC test set will be prepared and connected to the bonding cable terminal of the first phase to be tested. Check that the test set is grounded. The voltage will be raised gradually but within 5-10 seconds to 10kV

The stopwatch will be started. Occasional adjustment of the applied voltage may be necessary to avoid exceeding 10kV. At about 55 seconds, the leakage current will be noted. At 60 seconds the applied voltage setting will be quickly reduced to zero. The HV source will be switched off to apply the test set integral grounding to the tested cable. The cable will be discharged automatically as indicated by the voltmeter.

Before handling the test connection at the link box a ground will be applied manually to ensure that complete discharge has been achieved.

The test connection will be transferred to the next phase to be tested and the foregoing repeated.

The IR measurements of the cable sheaths will be repeated after the 10kv tests and the obtained values are noted.

Cable Insulation Resistance Test

·        Test Purpose: To ensure the soundness of the cable insulation, prior to performing the high voltage tests on the cable and after the high voltage test, cable insulation resistance by Mega ohmmeter shall be measured by applying DC 5kV for 1 minute between cable conductor and the metallic sheath under test with the adjacent cable conductors and sheaths grounded as shown in Figure.

Sponsored:


·        Test Equipment: Megger (BM21 or NIEAF Mega ohmmeter or Equivalent)
·        Requirement: Measured cable insulation resistance should be higher than the calculated value and put on record.
Cable Insulation Resistance Test
Procedure
This test shall be performed after completion of all splices/terminations installation with all cable conductors and metallic sheaths of the test end grounded except the cable conductor under test as shown in Figure.

All cable conductors and sheaths at the remote end shall be free.

Minimum cable insulation resistance shall be determined by the Equation except D and d; D is the outer diameter of the cable insulation and d is the inner diameter of the cable insulation.


Equation:

Formula

Where,
R: Calculated Insulation Resistance in [MΩ]
ρ: Volume Resistivity of the Cable Jacket Insulation at 20, 1014 for XLPE or PE in[Ω-m]
D: Outer Diameter of the Cable Jacket in [mm]
d: Inner Diameter of the Cable Jacket in [mm]
L: Length of the Cable phase under test in [m]


Capacitance Measurement Test

·        Test Purpose: The purpose of this test is to compare the measured capacitance with the capacitance calculated value. Capacitance is measured in order to provide a basis for the calculation of energized cable charging currents as required for protection relay setting calculations.
·        Standard: IEC 62067 Section 10.10
·        Test Instrument: Fluke 187 or NIEAF Tera Ohm 5kV or Equivalent
·        Requirement: Corrected cable capacitance shall not exceed 0.227 μF/km specified
Cable Capacitance Measurement
Procedure
The connections to the cable to be measured must be affected as shown in below diagram. The Test Instrument line terminal will be connected to the phase conductor and the outer terminal to be connected to the metallic sheath of the same phase. The figure shows the arrangement of Cable Capacitance Measurement

Calculate the test result with the formula as follows:

 Equation:
clip_image012  in  μF/km

Where Cx is the measured capacitance of one phase of the cable circuit in μF, C is the calculated capacitance of one phase of the cable circuit per kilometer in [μF/km] and L is the route length in km.

High Voltage AC Test (On Soak)

·        Test Purpose: This test will be carried out to ensure that installed cables have no defects.
·        Standard: IEC 62067
·        Test Equipment: Substation System Voltage

Procedure
A.C. voltage test shall be applied for 24 hours with the normal operating voltage of the system without load.

AC voltage test of the insulation
The a.c test voltage to be applied shall be subject to agreement between the purchaser and the contractor. The waveform shall be substantially sinusoidal and the frequency shall be between 20Hz and 300Hz. The voltage shall be applied for 1 h, either with a voltage according to Table 10 or with 1,7 U0 depending on Practical operational conditions.

Alternatively, a voltage of Uo may be applied for 24 h.

NOTE- for installations that have been in use, lower voltages and/or shorter durations may be used. Values should be negotiated, taking into account the age, environment, history of breakdowns, and of carrying out the test.

2 comments:

  1. Detail information and testing procedure that will help for successful commissioning. Commissioning work is very exciting to energize the plant. Thanks, carry on...

    ReplyDelete
  2. I think this is one of the most important pieces of information for me. And I’m glad to read your article. Thank you for sharing. test tag perth

    ReplyDelete

WAZIPOINT:
Thank you very much to visit and valuable comments on this blog post. Keep in touch for next and new article. Share your friends and well-wisher, share your idea to worldwide.

You may like the following pages